Saturday, September 17, 2011

Our Little House on The Prairie: Sept 12 - 16


It was an exciting week! The week kicked off with tile in the kitchen and master bath. I just realized I got so excited about everything else that I never took a good picture of the floor! The week ended with cabinets...and a few extras, too!
Master Bath (Condoo) Vanity & Tile
Master Bath door to closet (which is locked!) and linen cabinet
Kids' bathroom with vanity, tile and light (still trying to decide if it's upside down!)
Window trim in dining room!
KITCHEN!!!!! Woot!!! (Cabinets still wrapped will eventually be part of the "bar" that comes out on the left)
Laundry room cabinets and pocket door
Laundry room cabinets - I'm going to admit I almost passed out when I saw these. It's like another mini kitchen!!
Door to playroom
Closet trim in playroom
Siding!
Mantel!
1/2 bath vanity, tile and light (upside down? maybe!)
Trim work in Austin's room
Central vac!
And last but not least.... no more corn in our back yard! Now we can keep tabs on our rowdy neighbors! (Hee hee!!)

Up next:
This weekend: Hardwood!!!
Next week: Finish siding, trim, doors, etc. Living room furniture is being delivered on Tuesday (it will have to be stored for a few weeks) and appliances come on Thursday!!

Monday, September 12, 2011

Our Little House on The Prairie: Sept 5 - 9

It was an exciting week on our little homestead!
Brick, Day 5 (They worked on Labor Day!)
Brick, Day 6
JP's Room!
Austin's Room!
Dining Room, Living Room and Kitchen - all painted!
Playroom!
Electric was ran into the house!
Lots and lots of supplies delivered for the coming week!
And the Brick is complete!!
No one should be bored in the upcoming weeks... cabinets, doors, trim, lights and siding....
Condoo!
Condoo bathroom!
Cabinets!
Lots of cabinets!
Fireplace marble and mantel
Outlets!
Marble for Condoo Shower!
Austin and JP's bathroom

Up next: flooring, cabinets, more electrical work, fireplace and siding. Things are really moving along now!



Monday, September 5, 2011

Our Little House On The Prairie: Aug 29 - Sept 2

The day we thought would never come....has finally come!!! Brick work was started last Tuesday!
Brick, Day 1
Brick, Day 2
Plaster is complete!!
Back patio is poured!
Brick, Day 3
Finalizing paint colors!
Material for living room and dinning room!
Final paint choices (except for Condooo)!
Brick, Day 4
It was well worth the trouble!!!
Up next week: Paint, more brick work and electric!




Saturday, August 27, 2011

Our Little House on The Prairie: Aug 22 - 26

Close your eyes....
*
*
Open your eyes....
*
*
Look! Brick!!!
 
After many many hours of driving around and many different choices being shot down (out of stock, doesn't lay right, not enough bricks, etc...) we FINALLY have brick at our house!

And garage doors!

Plaster was also started this week! The plasterer thinks he'll be done in 8 - 10 days so we're looking at a completely plastered house by the end of next week!
 The north side of the house (bedrooms, master bath, kid's bath) were complete by the end of the week!

And the rest of the brick supplies were delivered. Brick layer call tonight (Saturday) to say he'd be there at 7:00 am on Tuesday morning to get started. It should take 10 business days to lay all 10,000 bricks. 

Plaster board was hung going down the garage steps

Ductwork in the basement...

I had to take this picture because Jay said we would NEVER have a window unit in our new house!

Coming up next week: Paint choices, finalize lights and fireplace marble, more plaster work and BRICK!!! Estimated move in date is Oct 1!
(JP found her way into this picture!)